Dear TRNSYS users,
thank's for your help... I found the problem! It
was in the definition of an opportune clo factor: to assume a mean value for
this parameter during the intermediate it's necessary to obtain a regular PMV,
so I defined a schedule...
Maurizio Sorce
Department of Energy and Environmental Research
(DREAM)
Università degli Studi di Palermo
----- Original Message -----
Sent: Monday, May 10, 2004 3:33 PM
Subject: PMV in PREBID
Dear TRNSYS users,
I'm simulating a radiative floor system defining
an active layer with the specific function of PREBID. When I choose as output
of the type 56 the Predicted Mean Vote I obtain an unespected result: in
the heating/cooling seasons PMV is in the range -0,3/0,3, but in the
intermediate (when the equipment is OFF) PMV reaches hight values (more than
-1,5/1,5).
Anyone can help me to understand this strange
behavior?
Thanks in advance
Maurizio Sorce
Department of Energy and Environmental Research
(DREAM)
Università degli Studi di Palermo