Quoting Fardin <trnsys15@hotmail.com>:
Hello Fardin,
you have to set the simulation time to 175200 and you have to pay attention
that the data files you use also are prepared for 20 years. Best way is to
create a file that reads for example the weather data 20 times (which means it
has to contain the right path and then it should be written in this data file
20 times).
Example:
FILE=
c:\trnwin\weather\stockhlm\stockhlm.try
c:\trnwin\weather\stockhlm\stockhlm.try
c:\trnwin\weather\stockhlm\stockhlm.try
etc
Good luck and Merry Xmas,
Rainer Tepe
Büro für Wärmetechnik BfWT
www.bfwt.com
>
> Hi and Thanks David for your quick respond
> How can I simulate the system operation for more than one year in TRNSYS?
> For 1-year simulation I put 8760hr as simulation stop time parameter now if
> I want my simulation for 20-year what should I do?
>
> regard